Preventive Maintenance
|
Preventive Maintenance - Software and Strategies Table of ContentsPreventive Maintenance - Anatomy of a Machine FailureTo further the discussion of Automated Maintenance Diagnostics we must first define the anatomy of a machine failure. The time between the occurrence of a failure and its full repair is divided into four periods.
Periods 1, 2, and 3, are the most critical because this is when the biggest damage to products and machines occur. Let’s look at the effects on each time period:
The results are shown in the following graph: The first three periods were reduced an average of 90% and the fourth period was reduced 20% as shown in the right-hand side of the graph.
Below is the analysis of a bread line producing 7200-7800 loaves per hour.
Additionally if we consider a typical bread line has 80-100 hrs of downtime per year and we further calculate 100 hours times $5,000 per hour, times 34% savings, we have saved $170,000 for the year.
Preventive Maintenance - Software and Strategies Table of Contents Machine Maintenance Software - Computerized Maintenance |
|
COGZ Systems, LLC
Phone 203-263-7882 Fax 203-263-7885 Woodbury,